Security

In excess of 300 projects completed in these sectors

Security

BGC Centre (28 The Esplanade Perth)

Project: To replace the DKS Access Control System.

Replacement of DKS Key Access Control System with Pro-Watch Security Management System using ‘PW-5000’ Intelligent Controllers and Proximity Card Readers to replace MIL equipment.  Proximity Card technology was used to replace the DKS Keys.

This site was completed and has been operational since December, 2006
with the following configuration:

Access Control Points
44 Doors
6 Lifts

 

Security

Quayside on Mill (2 The Esplanade Perth)

Project: To replace the DKS Access Control System.

Replacement of DKS Key Access Control System with Pro-Watch Security Management System using ‘PW-5000’ Intelligent Controllers and Proximity Card Readers to replace MIL equipment.  Proximity Card technology was used to replace the DKS Keys.

Access Control Points
25 Doors
6 Lifts

 

 

 

Security

 

Reserve Bank Building (45 St Georges Tce, Perth)

Project: To upgrade all Access Control systems and install a new lift control system with future integration to the video system.

Installation of security field panels consisting of ‘PW-5000’ Intelligent Controllers and Reader Modules supported by the Pro-Watch Security Management System software.

This site was completed and has been operational since October, 2002 with the following configuration:

Access Control Points
63 Doors
4 Lifts
CCTV Cameras Points
14 Fixed
2 PTZ
3 System (Slave) Workstations

 

 

Security

Ernst & Young Office Tower

Project: New installation of an Electronic Access Control and CCTV System for the “base building” and separate Electronic Access Control System for the major tenant of the building.

The base building comprises of security field panels consisting of ‘PW-5000’ Intelligent Controllers and Reader Modules and supported by Security Management System software. The base building system controls building access and after hours air-conditioning call.

The tenants system comprises of security field panels consisting of Lennel Intelligent Controllers and Reader Modules and supported by Security Management System software.

This site was completed and has been operational since January 2006 with the following configuration:

Access Control Points
50 Proximity Card Readers
4 Lifts
CCTV Cameras Points
34 Fixed
2 PTZ
2 System (Slave) Workstations

 

 

Alinta Plaza

Project: New installation of an Electronic Access Control and CCTV System for the “base building” and separate Electronic Access Control System for the major tenant of the building.

The base building comprises of security field panels consisting of ‘PW-5000’ Intelligent Controllers and Reader Modules and supported by Pro-Watch Security Management System software. The tenants system comprises of security field panels consisting of Concept 4000 Intelligent Controllers and Reader Modules and supported by Insight Security Management System software.

This site was completed and has been operational since March 2006.

Access Control Points
19 Doors
3 Lifts
CCTV Cameras Points
14 Fixed

 

 

Security

London House

Project: To replace the MIL Key Access Control System.

Replacement of MIL Key Access Control System with Pro-Watch Security Management System using ‘PW-5000’ Intelligent Controllers and Proximity Card Readers to replace MIL equipment. Proximity Card technology was used to replace the MIL Keys.

This site was completed and has been operational since May, 2006 with the following configuration:

Access Control Points
46 Doors
5 Lifts

 

Quick links